Hydraulic Excavator Earthwork Production Rate (BCY / LCY / TPH) Calculator

Easily calculate and compute hydraulic excavator earthwork production rate (bcy / lcy / tph) calculator with accurate equations, live formulas, and expert guidance.

Standard cycle: Dig, swing 90°, dump into truck, return (18-26 seconds).

Common earth: 90-100%; Hard clay: 80-85%; Blasted rock: 60-75%.

Standard 50-minute hour accounts for truck spotting and repositioning.

Calculated Result
307 LCY / hour

Hourly Production Rate

Hourly Production Rate

307 LCY / hour

Hourly Production Lcy

307

Hourly Production Tons Tph

399

Cycles Per Hour

136

307 — LCY / hour

Calculation Breakdown

  1. Applied FormulaEstimates heavy civil earthmoving production rates in loose cubic yards (LCY) and tons per hour for crawler excavators.Q = \left(\dfrac{t_{\text{work}}}{t_{\text{cycle}}}\right) \times V_{\text{bucket}} \times \eta_{\text{fill}}

Excavator Production Metric Output

Interactive visualization based on your current inputs

Calculated Value
0.077154230307Hourly Production Rate

What Is the Hydraulic Excavator Earthwork Production Rate (BCY / LCY / TPH) Calculator?

This tool computes hydraulic excavator earthwork production rate (bcy / lcy / tph) calculator with high precision arithmetic.

How Does the Hydraulic Excavator Earthwork Production Rate (BCY / LCY / TPH) Calculator Work?

Estimates heavy civil earthmoving production rates in loose cubic yards (LCY) and tons per hour for crawler excavators.

Hydraulic Excavator Earthwork Production Rate (BCY / LCY / TPH) Calculator Formula & Variables

The core mathematical equation utilized by this calculator is expressed as:

Q=(tworktcycle)×Vbucket×ηfillQ = \left(\dfrac{t_{\text{work}}}{t_{\text{cycle}}}\right) \times V_{\text{bucket}} \times \eta_{\text{fill}}

Estimates heavy civil earthmoving production rates in loose cubic yards (LCY) and tons per hour for crawler excavators.

How to Use the Hydraulic Excavator Earthwork Production Rate (BCY / LCY / TPH) Calculator

  1. Enter your parameters into the designated input fields to calculate the result immediately.

Step-by-Step Example Calculation

Hydraulic Excavator Earthwork Production Rate (BCY / LCY / TPH) Calculator Example

Input Values:

bucketCapacityCubicYards:2.5
cycleTimeSeconds:22
bucketFillFactorPercent:90
jobEfficiencyMinutesPerHour:50
Worked Steps: Sample evaluation based on standard reference conditions.

Understanding Your Result

The calculated primary figure indicates the optimal or required LCY / hour.

Factors That Affect the Result

  • Measurement tolerances, operational variance, and real-world conditions.

When Should You Use This Calculator?

  • Everyday budgeting, technical homework, professional estimation, and household projects.

Assumptions & Limitations

  • Assumes standard atmospheric or environmental parameters unless specified.

Frequently Asked Questions

Calculation Accuracy & Reference Note

Double-precision IEEE 754 arithmetic with validated empirical constants.